| Milestone | Date | Notes |
| Mobilize to Site | | Achieved |
| Shoring Pile Start | | Achieved |
| Erect Tower Crane | | Achieved |
| Pour Mat Footing – North | | Achieved |
| Pour Level 1 Deck – North | | Achieved |
| Curtain Wall Start Level 2 | | Achieved |
| Elevator Start | | Achieved |
| Start Finishes Level 2 | | Achieved |
| Concrete Structure Topout Level R4 | | Achieved |
| Building Envelope Start | | Achieved |
| Drywall Start | | Achieved |
| Vertical Transportation Start | | Achieved |
| Above Grade Structure Complete | 05/31/22 | |
| Dismantle Tower Crane | 09/27/22 | |
| Dismantle Manlift | 09/27/22 | |
| Substantial Completion | 04/06/23 | |