Mat footing concrete pour to take place this weekend beginning at
12:01am 10/26/19. This activity will require the closure of 8th ave as
well as Columbia Street. Uninterrupted access will be maintain to the
entry exit of the skyline parking garage. No closure will be required of
any sidewalks beyond our normal closures.
Time Line of Activities:
· 12:01 Close streets / Mobilize Equipment
· 2:00am Begin Concrete Pour
· 9:00AM Complete Pour
· 12:00pm Reopen Streets
· Operation Complete