Notice: 11/23/2019 – 12/15/2019

Notice: 11/23/2019

Mat footing concrete pour to take place the  weekend  of November 23rd beginning at 12:01am. This activity will require the closure of 8th ave as well as Columbia Street. Uninterrupted access will be maintain to the entry exit of the skyline parking garage. No closure will be required of any sidewalks beyond our normal closures.

Time Line of Activities:

  • 12:01 Close streets / Mobilize Equipment
  • 2:00am Begin Concrete Pour
  • 2:30pm Complete Pour5:30pm Reopen Streets
  •  Operation Complete

Notice: 12/14/2019
Tower crane erection will take place the weekend of December 14th. This work will require the closure of 8th ave as well as Columbia Street. Uninterrupted access will be maintain to the entry exit of the skyline parking garage. No closure will be required of any sidewalks beyond our normal closures.

Time Line of Activities:

December 14th

  • 3:00am Close streets / Mobilize Equipment
  • 3:00am Set Up Mobile Crane
  • 5:30am Build Tower Crane
  • 7:30pm Complete Crane Build
  • 7:30pm reopen Streets
  • Operation Complete

December 15th

  • 6:00am Testing and Certification of Tower Crane
  • 4:30pm Operation complete