Notice: 11/23/2019 – 12/15/2019

Notice: 11/23/2019

Mat footing concrete pour to take place the  weekend  of November 23rd beginning at 12:01am. This activity will require the closure of 8th ave as well as Columbia Street. Uninterrupted access will be maintain to the entry exit of the skyline parking garage. No closure will be required of any sidewalks beyond our normal closures.

Time Line of Activities:

  • 12:01 Close streets / Mobilize Equipment
  • 2:00am Begin Concrete Pour
  • 2:30pm Complete Pour5:30pm Reopen Streets
  •  Operation Complete

Notice: 12/14/2019
Tower crane erection will take place the weekend of December 14th. This work will require the closure of 8th ave as well as Columbia Street. Uninterrupted access will be maintain to the entry exit of the skyline parking garage. No closure will be required of any sidewalks beyond our normal closures.

Time Line of Activities:

December 14th

  • 3:00am Close streets / Mobilize Equipment
  • 3:00am Set Up Mobile Crane
  • 5:30am Build Tower Crane
  • 7:30pm Complete Crane Build
  • 7:30pm reopen Streets
  • Operation Complete

December 15th

  • 6:00am Testing and Certification of Tower Crane
  • 4:30pm Operation complete

Notice 10/23/2019

Mat footing concrete pour to take place this weekend beginning at 12:01am 10/26/19. This activity will require the closure of 8th ave as well as Columbia Street. Uninterrupted access will be maintain to the entry exit of the skyline parking garage. No closure will be required of any sidewalks beyond our normal closures.

Time Line of Activities:

·         12:01 Close streets / Mobilize Equipment
·         2:00am Begin Concrete Pour
·         9:00AM Complete Pour
·         12:00pm Reopen Streets
·         Operation Complete

Notice: 9/4/2019

We are currently at the bottom of the excavation.  The crane foundation has been excavated and will be poured on 9/21/19.  The crane foundation will be a continuous pour and occur on a weekend.

Notice: 7/26/2019

There is about 12 more feet of soil removal required to get to the bottom of the excavation.  The contractor will finish placing tie backs in the next few weeks.   Once at the bottom of the excavation, the contractor will begin laying the matt slab and then start upward with concrete to finish the parking garage. 

A crane foundation will be installed.  The crane that will be installed is similar to the building at 2nd and Stewart, the crane will be free standing for several floors. 

Notice: 6/26/2019

Due to the testing of soil, Turner is one day behind schedule. Turner expected to average 5,100 yards of soil per day during 8 weeks of excavation. Turner hopes to make-up the one day and get back on schedule.

Notice: 5/22/19

Construction will begin on 5/22/19.  The parking element will be put in place.  Turner will begin with two rigs on site and drill holes that will eventually hold the tieback.